As part of the ongoing Phase 2 construction work, the contractor will close Wilson Blvd at the SR 72 intersection for approximately 2 days to complete…
As part of the ongoing Phase 2 construction work, the contractor will close the southerly Delaware Route 71 leg of the Delaware Route 72 and Delaware …
As part of the ongoing Phase 1 construction work, the contractor will close the northerly Delaware Route 71 leg of the Delaware Route 72 and Delaware …
As part of the ongoing Phase 1, Stage 1 construction work, the center pavement of SR 72 will be reconstructed from about 500’ east of American Boule…
As part of the ongoing Phase 1, construction work, improvements will be made to the Kathleen Wilbur Elementary School Entrance. The…
As part of the ongoing Phase 1 construction work, the center pavement of SR 72 will be reconstructed from just east of American Boulevard/Connell Driv…
The weekend work and detours scheduled for the weekend of November 18th to November 21st have been cancelled and will be resched…
Nighttime pavement patching operations will occur Monday through Thursday throughout the week of October 3rd.
<...
Project Construction will begin with nightwork the week of September 19th. The work will include a hot-mix pavement overlay of the southbou…
DelDOT is holding a public information session to update the public on construction of the SR 72 Improvements Project.
The public is invited to att…